To install the STAHL 253858 Series 8118 Junction Boxes, follow these steps:
1. Ensure that you have all the necessary equipment for installation, including the junction box itself, cable glands (plastic or metal), and any optional miniature fuses.
2. Determine the appropriate location for the junction box installation, considering the electrical connections and the required IP66 degree of protection.
3. Prepare the cables by stripping the insulation and crimping core end sleeves if necessary.
4. Choose the appropriate cable glands for the entry points of the junction box. The product manual suggests using 2 x 8161/7-M25-1707-LT cable glands with plugs for both Entry 1 and Entry 2.
5. Install the cable glands by inserting them into the entry points and tightening them securely.
6. Connect the cables to the mantle terminals inside the junction box. The number of conductors and the permissible cross-sections depend on the specific terminal size. Refer to the product manual for the exact details.
7. If desired, install miniature fuses in the junction box for additional safeguarding. This is an optional feature.
8. Once all connections are made, ensure that all conductors have identical cross-sections and materials.
9. Securely xxxx on the cover of the junction box using M4 stainless steel screws. The manual recommends a tightening torque of 1.4 Nm.
10. Verify that the installation is complete and all connections are secure.
Please note that this answer is based on the information provided in the product manual. For specific installation details and safety guidelines, refer to the official STAHL 253858 Series 8118 Junction Boxes Installation Guide.