Before installing the GIBRALTAR BUILDING PRODUCTS CPSRD2B Steel Fascia Gutter, it is important to prepare the fascia board and metal drip edge. Here are the steps you need to follow:
1. Remove old gutters: Start by removing any existing gutters from the fascia board.
2. Inspect fascia board and metal drip edge: Check the condition of the fascia board and metal drip edge. If there are any damages or issues, repair or replace them as needed.
3. Measure and mark with a chalk line: Use a chalk line to measure and mark the desired position for the gutter installation. This will ensure that the gutter is installed straight and level.
4. Tack a string to the fascia board: Tack a string to the fascia board, around 4 or 5 inches below the roofline. Make sure the string is straight, level, and taut. Drop one end of the string 1/4 inch per 10 ft, sloping toward the downspout.
By following these steps, you will properly prepare the fascia board and metal drip edge for the installation of the GIBRALTAR BUILDING PRODUCTS CPSRD2B Steel Fascia Gutter.