To install the LEDALITE Verge Suspended LED fixtures, follow these steps:
1. Prepare Fixtures / Install ceiling mounting components: Arrange the fixtures in the specified mounting locations and install all ceiling mounting components and vertical aircraft cables according to the separate installation instructions for Aircraft Cable Mounting.
2. Install End-of-Row Aircraft Cable Brackets: Hook the A/C mounting bracket to the endplate and raise it until the security tab is engaged. Attach the bracket to the fixture using the supplied fastener.
3. Suspend & Level First Fixture: With two people, raise the first fixture to the ceiling. Insert the aircraft cable through the aircraft cable adjuster located on the A/C mount bracket. The adjuster will automatically grip and hold the cable. Trim the cable below the adjuster as instructed.
4. Complete Electrical Connections: Cap all wires and tuck them into the wire cavity for non-power locations. For power locations, remove the required 1/2" round knockout(s), insert the power cord, and apply strain relief. Complete the electrical connections using wire nuts. Tuck the wires into the wire cavity.
5. Install in-row mount brackets and insert joiner aligners: For each additional fixture in the row, attach the A/C mounting bracket to the fixture using the supplied fasteners at the end furthest from the existing suspended fixture. At the end closest to the existing fixture, insert joiner aligners into the crossplate.
6. Suspend and join additional fixtures to create a row: With two people, raise the second fixture to the ceiling. Insert joiner aligners through the black gasket and into the suspended fixture at the joint. At the other end, insert the aircraft cable through the adjuster.
7. Complete electrical connections at joints: Complete the in-row electrical connections using the supplied quick-wire connectors for non-power locations. For power locations, remove the installed quick-wire connectors and complete the electrical connections using wire nuts. Tuck the wires into the wiring cavity.
8. Secure Joints: Secure the joints from above using the supplied nut and bolt hardware.
9. Install endcaps: Attach the end caps using the supplied #8 screws. Do not over-tighten the endcap fasteners.
10. Install Light Guide: Identify the smooth side of the Light Guide and ensure it is installed smooth side down. Install the Light Guide panel into the LED fixture after joining and wiring is complete. Ensure the panel is seated correctly.
Please refer to the LEDALITE Verge Suspended LED Instruction Manual for more detailed instructions and illustrations.