To install the DIEHL ALTAIR V4 IS T90 Volumetric Water Meter, please follow the installation instructions provided in the instruction manual. Here is a step-by-step guide:
1. Prepare the installation location: Ensure that the installation location is suitable and meets the necessary requirements. The meter should be installed in a vertical position, with sufficient space for maintenance and reading.
2. Shut off the water supply: Before installation, make sure to shut off the water supply to prevent any water flow during the installation process.
3. Install the meter: Connect the meter to the water supply line using appropriate fittings and ensure a secure connection. It is recommended to use a non-return valve to prevent backflow.
4. Connect the wiring: If applicable, connect the wiring according to the electrical connection diagram provided in the manual. Ensure proper grounding and follow any local electrical regulations.
5. Perform initial tests: After installation, open the water supply and check for any leaks or abnormal readings. Make sure the meter is functioning properly.
6. Seal the meter: Once the installation is complete and verified, seal the meter to prevent tampering or unauthorized access. Follow any local regulations regarding sealing procedures.
Please note that these are general installation instructions, and it is important to refer to the specific instructions provided in the DIEHL ALTAIR V4 IS T90 Volumetric Water Meter instruction manual for accurate and detailed installation steps.