To assemble the PCE-DFG FD 300 Force Path Adaptor onto the PCE-MTS 500 material test stand, please follow these steps:
1. Check the delivery scope for completeness. A list of all components can be found in the manual.
2. Attach component (1) to component (3) using two screws (component 10).
3. Pre-mount the set screws (components 11 + 12).
4. Attach the previously mounted module to the crossbeam of your PCE-MTS 500 test stand.
5. Insert component (4) into the groove of component (1) and loosely fix them with two screws (component 10).
6. xxxx component (2) onto the module from the back with four screws (component 10). Make sure that components (4) are properly placed in the groove of component (2). Do not fully tighten the screws on components (4) yet.
7. Place component (5) on the rail of the PCE-MTS 500 test stand, above the module. Attach component (6) to component (5) and fix both components with screws (component 9).
8. Attach component (7) to component (5) with screws (component 10).
9. Repeat the same steps below module (1) to attach the module to the PCE-MTS 500 test stand. Slide the two components (4) against the rail and fix the pre-fastened screws.
10. Insert the measuring module (component 8) into the assembled module. Slide the lower holder and the upper holder onto the ends of the meter and tighten all screws (attachment to the rail and meter).
11. Lock the measuring module vertically with the pre-mounted set screws.
Now, the PCE-DFG FD 300 Force Path Adaptor is ready for use and can be used as described in the user manual.
Please refer to the manual for detailed illustrations and further instructions on the assembly process.