To install the ZEVNI A04903 6-Light Gold Modern-Contemporary Chandelier, please follow the steps outlined in the provided installation guide. Here is a summary of the installation process:
1. Safety precautions: Before starting the installation, make sure to turn off the electricity at the main fuse or circuit breaker box. Also, ensure that the mounting surface is clean, dry, flat, and strong enough to support the weight of the chandelier.
2. Pre-installation: Assemble the various parts of the chandelier. This includes threading connector-A into the iron ring, threading connector-B into the smaller glasses, and attaching screws to the bigger glasses. xxxx the fixture loop assembly and stem together onto the top of the sockets assembly. Hang loop rods on the fixture loop assembly and attach quick links to the loop rods and iron ring.
3. Determine hanging height: Measure and determine the correct number of links needed for the desired hanging height. Use chain pliers to disconnect and discard any unwanted parts of the chain. Attach a quick link to the chain and loop on the top of the fixture loop assembly.
4. Weave the wires: Carefully weave the fixture wires through the chain, going in and out of every other link. Stop just when you reach the top of the chain. Gently pull the wires to ensure they are not stressed.
5. Turn off power: Before proceeding with the installation, make sure to turn off the electricity at the main fuse or circuit breaker box.
6. Installation: Remove the collar ring from the collar loop. Attach the single bar to the outlet box using the provided mounting screws. Raise the canopy over the collar loop and xxxx the collar ring to measure the proper position. Pass the chain through the collar ring and canopy. Open a quick link, attach it to the collar loop, and pass the fixture wires through the collar loop to the top of the pre-assembled threaded xxxx . Ensure the wires are not stressed.
7. Wire connections: Connect the wires according to the provided wiring diagram. Make sure to connect the ground wire (bare copper wire) separately and never connect other wires to the ground wire. Twist the wires together with plastic wire connectors, wrap each connector with electrical tape, and tuck all wires into the outlet box.
8. Secure the canopy: Raise the canopy to the ceiling and secure it in place by tightening the collar ring onto the collar loop.
9. Install bulbs: Install the appropriate bulbs (not included) into the sockets. Make sure not to exceed the maximum recommended wattage for each socket.
10. Final check and testing: Double-check that everything is installed properly before turning on the power. Once everything is confirmed, you can turn on the light and enjoy your new chandelier.
For any further assistance or inquiries, you can contact the customer care team at +1 850 296 2377 or email homecustomercare@outlook.com during working hours (Mon - Fri 9:00 - 16:00 EST).