Answer

Mar 06, 2025 - 09:34 PM
To install the STAHL 136899 Exe Terminal Box, please follow the steps below:
1. Ensure that the installation location is suitable for the terminal box and meets the specified ambient temperature range (-60 °C to +40 °C for T6, -60 °C to +55 °C for T5, -60 °C to +70 °C for T4).
2. Determine the desired entries installation options/side. The manual states that this specific model comes without drilled holes for entries.
3. Prepare the necessary components for installation. The terminal box comes with a terminal rail (35 x 637 mm) and type of terminals (1 x Phoenix UT, 2-conductor, 4 mm², grey). It also includes an earth rail (18 x 4 mm², 2x).
4. Position the terminal box in the desired location and ensure it is securely mounted.
5. Connect the desired electrical components to the terminal rail using the provided terminals.
6. If required, install any additional spare parts such as brass plates or flanges according to the specific needs of your installation. Refer to the spare parts section of the manual for the appropriate part numbers.
7. Once all components are properly installed, ensure that the cover screws are tightened to a torque of 4.5 Nm.
Please note that this is a general overview of the installation process. For more detailed instructions and specific information, refer to the STAHL 136899 Exe Terminal Box Instruction Manual provided.