To install the STAHL 136802 Ex e Terminal Box, please follow the steps outlined in the owner's manual provided. Here is a general guide:
1. Ensure that the installation location is suitable for the terminal box and complies with the specified ambient temperature range (-60 °C to +40 °C for T6 or -60 °C to +55 °C for T5).
2. Make sure the power supply to the terminal box is switched off before starting the installation.
3. Determine the appropriate entry points for cables or conduits based on your specific requirements. The terminal box does not come with pre-drilled holes, so you will need to drill them yourself if needed.
4. Connect the cables or conduits to the terminal box using appropriate connectors or glands. The terminal box is designed to accommodate a connection cross-section of 4 mm² (AWG 12).
5. If required, mount the terminal rail (35 x 301 mm) inside the terminal box using the provided mounting holes.
6. Customize the equipping of the terminal box according to your specific needs. The terminal box can be equipped with series terminals up to 300 mm².
7. Once the installation is complete, ensure that all connections are secure and properly tightened.
8. Finally, restore the power supply and test the functionality of the terminal box.