To install the Vulcan VIR1BF V Series HDR Broiler, follow these steps:
1. Unpack the broiler and check for any shipping damage. Contact the carrier if any damage is found.
2. Verify that the electrical service and gas supply (natural or propane) match the specifications on the rating plate.
3. Ensure that the installation location allows for proper clearances and ventilation.
4. Install the ceramic radiant bricks, if applicable, by placing them on the rails alongside the burners.
5. Follow all installation codes and standards, including local codes and the National Fuel Gas Code.
6. If the broiler is mounted on casters, use a flexible connector and quick-disconnect device that comply with the appropriate standards.
7. Level the broiler from front to rear and side to side using a carpenter level.
8. Connect the gas supply to the broiler, ensuring that all joints are leak-free.
9. Install pressure regulators with the correct outlet pressure for natural gas or propane gas.
10. Make sure the flue duct is not obstructed and consider installing a ventilation system for flue gases.
11. Follow the electrical connection guidelines, ensuring compliance with the National Electrical Code and local electrical codes.
12. Before lighting the broiler, make sure the gas supply is turned off and follow the lighting instructions provided in the manual.
Please note that these are general installation guidelines. For more detailed instructions and specific requirements, refer to the .