To install the Felicity Solar LiFePO4 Battery System for Households, please follow the steps below:
1. Unpacking and Inspection:
- Before installation, inspect the unit to ensure that nothing inside the package is damaged.
- Check that you have received all the necessary items mentioned in the manual.
2. Mounting the Unit:
- Select a suitable location for installation, ensuring that it is not mounted on flammable construction materials.
- The ambient temperature should be between 0°C and 45°C for optimal operation.
- The recommended installation position is to adhere the battery to a vertical wall.
- Ensure that there is enough space for heat dissipation and wire removal.
3. Connection for Parallel Mode:
- The LPBA battery supports parallel connection for expansion.
- If you need to connect multiple battery banks in parallel, follow the schematic diagrams provided in the manual.
- Connect the batteries as shown in the diagrams, and ensure proper communication terminal connections.
4. Recommended Settings:
- Before connecting devices such as inverters, MPPT charger controllers, or UPS to the battery pack, implement the recommended settings.
- Refer to the manual for the specific settings for the LPBA48100-IL model.
Please note that these are general installation instructions. For detailed instructions and safety guidelines, please refer to the Felicity Solar LiFePO4 Battery System for Households User Guide.