To install the smartcell SC-51-0100-0001-99 Fire Manual Call Point, follow these steps:
1. Pre-installation:
- Ensure that the installation is done by a fully trained competent person and in accordance with applicable local installation codes.
- Take precautions when handling electronic boards to prevent damage from Electrostatic Discharge (ESD).
- Consider using a non-metallic spacer if mounting the device on a metal surface.
- Fit the breakable tag after installation and testing of the device.
- Use the product within the specified environmental operating conditions.
2. Components:
- The smartcell SC-51-0100-0001-99 Fire Manual Call Point comes with a transparent cover, fire manual call point, mounting plate, Allen key, reset key, breakable tags, and batteries (not included in some regions).
3. Remove mounting plate:
- Carefully unclip the two sections of the device, observing the hinged connection at the top.
4. Fix mounting plate:
- When fixing the device to the wall, use all four fixing positions to ensure a firm fixing.
- Alternatively, there are two alternative fixing positions available for fixing to existing electrical mounting boxes.
- Observe the orientation marking as shown.
- Use suitable fasteners and fixings.
5. Fit batteries:
- When fitting or replacing batteries, observe the correct polarity and use only specified batteries.
6. Configuration:
- The device must be added (programmed) to the control panel.
7. Completing the installation:
- Reassemble the unit, observing the hinged connection.
- Lock the device by turning the Allen key ANTI-CLOCKWISE until the xxxx is flush with the casework.
8. Testing and resetting:
- Test the device once it has been added (programmed) to the system.
9. Optional breakable tag fitting:
- Locate the end of the tag under the retaining clip and pull it through the cavity until the tag is secure.
- Carefully remove any excess using cutters.
10. Device unlocking:
- If the device is locked, turn the Allen key CLOCKWISE to release the locking mechanism.
- Once unlocked, carefully unclip the two sections.