To install the welldana PLP-REM Duratech Controller, follow these steps:
1. For a single PLP-REM unit:
- Connect a 12VAC magnetic transformer to the "12VAC FROM TRANSFORMER" terminal of the PLP-REM.
- Connect the pool lights to the "12VAC TO LAMPS" terminal in the PLP-REM.
- Install the included filter to the primary circuit (230VAC side) of the transformer.
- Make sure the total power load does not exceed the maximum rating of the "12VAC TO LAMPS" relay contact (58A x 12VAC = 696VA).
2. For multiple PLP-REM installation:
- If the total lamp power exceeds 700VA, multiple PLP-REM units can be linked together.
- Connect the PLP-REM units with each other using the CAN bus. Connect the CAN terminals of the first PLP-REM with the CAN terminal of the second PLP-REM. If more than 2 PLP-REM units are necessary, daisy chain each CAN terminal with the next PLP-REM unit.
- Set the DIP switches on the PLP-REM units to the correct MASTER/SLAVE setting. The first PLP-REM will be the MASTER, and the others will be SLAVES.
Please refer to the welldana PLP-REM Duratech Controller User Manual for more detailed installation instructions and diagrams.