Answer

Feb 28, 2025 - 06:50 AM
To install the AMPLENESS Home Energy Storage System Split Type, please follow these steps:
1. Unpacking Examination:
- Check the battery for any damage or missing parts. Do not install a damaged or incomplete battery.
- Compare the packing list with the actual contents of the package.
2. Installation:
- The wiring work must be performed by qualified electrical personnel.
- Ensure that the power is cut off before wiring.
- Install the cables according to the requirements and safety regulations.
- Lift and put down the battery gently to avoid damage.
- Keep the battery away from flammable objects and heat sources.
- Do not drop any debris into the battery during installation.
3. Working:
- Do not directly plug or unplug the DC input socket or other sockets to avoid electric shock.
- Do not directly open the battery shell to avoid electric shock.
- Ensure the battery is within the allowable range before operating.
- Fully charge the battery and disconnect the switch if not used for a long time.
- Regularly charge the battery and disconnect the switch after charging is completed if not used for a long time.
4. Maintenance and Overhaul:
- Disconnect the DC input, DC output, and switch before disassembling the shell to avoid electric shock.
- Do not touch the exposed parts of the circuit as there may still be residual electricity.
- Seek professional personnel for maintenance and overhaul. Do not disassemble the battery yourself.
5. Transportation:
- Avoid strong vibration, falling, and bumping during transportation.
- Do not place the package upside down.
- Do not lose any accessories and the user manual during unpacking or transportation.
Please refer to the complete user manual for more detailed instructions and safety precautions.
Add New Comment