To install the APC-790 and APC-890 Heavy Duty 24V System Articulated Arm, follow the steps outlined in the instruction manual. Here is a summary of the installation process:
1. Preliminary Checks:
- Ensure that the gate structure is suitable for automation.
- Make sure the gate leafs move properly and uniformly without any irregular friction.
- Check that the gate hinges are in good condition, with no rust or biting, and well greased.
- The gates should be able to be freely opened and closed before installing the automation system.
- Install a gate stop for the closed position.
2. Important Safety Information:
- Make sure there is sufficient space for the gate(s) to swing open fully.
- Install the control panel box within 9 meters of the motor and ensure it is not damaged.
- Do not use parts or components not supplied by the manufacturer.
- Check all wiring works before connecting the battery, solar panel, or transformer to the control panel.
- Turn off the power and disconnect the battery when doing maintenance.
- Ensure the control panel box is free from water leakage.
- Do not supply mains power directly to the motor, control box, or any accessories.
- Do not install the operating system if in doubt. Contact the manufacturer.
- Do not cross the gate while it is operating.
- Keep the remote controls in a safe place and away from children.
3. Tools Required:
- Refer to the manual for a list of tools required for installation.
4. Motor Layout Explained:
- Familiarize yourself with the different components of the motor layout as described in the manual.
5. Assembly Overview:
- Follow the instructions in the manual for assembling the components.
6. Rural Gate Installation Methods:
- Depending on your gate type (round post or tube gate), follow the instructions in the manual for installation.
7. Gate Stop Installation:
- Install a physical gate stop at the closed position before installing the gate motors. Follow the instructions in the manual for single or double gate systems.
8. Marking The Installation Levels:
- Use a spirit level/bubble level to draw horizontal lines across the gate rail and gate post. These lines will serve as guidelines for installation.
9. Post Bracket Installation:
- Position the motor mounting bracket on the post or pier using the marked lines as a guide. Mark and drill the fixing holes, then use appropriate fixing hardware to secure the bracket.
10. Installing the Motor(s):
- Mount the motor onto the post bracket using the provided nuts and bolts.
11. Manual Override:
- Insert the manual override assembly onto the override spline and turn it 45° towards the front of the motor to disengage the motor.
12. Installing the Primary Arm:
- Attach the primary arm to the motor spline shaft and tighten the grub xxxx to lock them together.
13. Arm and Gate Bracket Assembly and Fitting:
- Follow the instructions in the manual for assembling and fitting the arm and gate bracket.
14. Limit Switch Adjustment:
- Adjust the opening and closing limit switches as per the diagrams and instructions in the manual.
15. Wiring:
- Follow the wiring diagrams provided in the manual based on whether it is a pull-to-open or push-to-open installation.