To use the NAKANISHI CTS-3030 Coolant Through Spindle, follow these steps:
1. Install the appropriate collet and collet nut for your tool. Refer to the options section in the instruction manual for the specific part numbers.
2. Connect the high-pressure pump, intake filter, intake hose/filter, high-pressure coolant hose, high-pressure coolant fitting, coolant hose, hose fitting, and manifold block as recommended in the example of the recommended combination.
3. Set the desired coolant pressure on the high-pressure pump within the range of 3.0 - 20.0 MPa.
4. Insert the tool with the coolant through drill into the spindle, ensuring it is securely held by the collet and collet nut.
5. Set the desired spindle speed on the machine control within the maximum rpm of 30,000 min-1.
6. Start the coolant flow by activating the high-pressure pump.
7. Begin the drilling operation, taking advantage of the benefits of internal coolant such as improved chip discharge, extended tool life, reduced drilling time, and high precision.
Note: The instruction manual provides additional information on drilling data, comparisons between conventional drilling and coolant through drilling, and drilling examples on different work materials. It is recommended to refer to the manual for more detailed instructions and guidelines specific to your application.