Answer

Feb 24, 2025 - 09:31 PM
The installation process for the RAB 2594 Bled Rectangular Bollard Light is as follows:
1. Location: The bollard should be mounted on a firm, level surface.
2. Anchor Bolts Installation: Install two anchor bolts in a concrete foundation using the provided template. The anchor bolts should protrude no more than 3 inches.
3. Mounting Fixtures: Loosen the three door screws and remove the door. Use the two #10-24 x 3/4" mounting screws to thread into the bollard extrusion. Secure the screws from inside the bollard using the provided nuts and lock washers. Ensure that the housing gaskets are properly positioned. Make electrical connections from the supply wires to the fixtures using approved connectors and strain relief the wires. Replace the door and tighten the screws. Install the bollard cap and gasket, then tighten the two set screws.
4. Mounting Plate: Assemble the fixture(s) to the bollard before mounting the bollard to the mounting plate. Place the mounting plate over the anchor bolts and use four leveling screws or shims to level the mounting plate. Tighten the assembly using the provided washers, lock washers, and nuts. Ensure that the supply leads extend far enough to make fixture connections. Slide the gasket down around the bottom of the mounting plate. Use the four mounting screws to mount the bollard to the mounting plate and tighten securely.
Please note that these instructions do not cover all details or variations in equipment, nor do they provide for every possible situation during installation, operation, or maintenance. It is crucial to follow the instructions provided in the manual and consult with a person familiar with the construction and operation of the product and the applicable installation code.