To mount the SEIFERT 6155305 BTU Thermoelectric Cooler on a control cabinet, please follow these steps:
1. Ensure that the power supply is switched off before starting any work on the unit.
2. Make sure that the flows of air leaving and entering the cooling unit, both internal and external, are not obstructed.
3. Before drilling the enclosure, ensure that the fixing elements and couplings will not interfere with the equipment inside the enclosure.
4. Once all mounting preparations are complete, you can proceed with the actual mounting operation.
5. Use the enclosed material provided to mount the unit on the cabinet.
6. Set the unit up on the cabinet, ensuring that the electrical connection is above the internal fan.
7. If the unit does not have a duct, xxxx the M6 locknuts and washers into the M6 set screws in the unit. If the unit has a duct, xxxx the M6 screws and washers into the M6 threaded rivets in the unit.
8. Ensure that the resistance of the earth connection between the cabinet and cooling unit is less than 0.1Ω.
9. Depending on the mounting situation, you may need to consider and adjust the condensation management.
10. To maintain the TYPE 4X rating, tighten the unit with a torque of 4.5 Nm, following the specified sequence.
11. Finally, ensure that the cut out dimension (244 x 428 mm) matches the dimensions of the unit.