To install the Sport-Thieme 111 8634 Aluminium Barrier, please follow the instructions provided in the manual. Here is a step-by-step guide:
1. Prepare the foundations: Each foundation should measure 300×300×800 mm, with a distance of 2,500 mm between the centers.
2. Coating the posts: The posts must be coated with bitumen or epoxy coal tar where they are set into concrete to prevent corrosion.
3. Anti-corrosion coat: Once the posts have been set in concrete, apply another anti-corrosion coat to the section where the aluminum and concrete join.
4. Setting the posts: Fill half of the moist-earth pit with B25 concrete and compress. Then insert the posts, align them, and fill the pits with concrete. Make sure the posts protrude by 1,100 mm above ground and are 2,500 mm apart (measured from center point to center point). Allow the concrete to set.
5. Adding handrails: Use the T-connectors provided to attach the handrails to the posts. Drill the holes as marked out on the T-connectors using a 5.0-mm-diameter drill, and then secure using three rivets per connector. The 90-degree bends at each end of the barrier do not require drilling or riveting.
6. Final checks: Perform a visual inspection regularly, tighten the xxxx connections routinely, and inspect the equipment for any damage. Replace worn parts as necessary.
Please note that these instructions are a summary of the manual. For complete and accurate installation guidance, refer to the Sport-Thieme 111 8634 Aluminium Barrier Instruction Manual provided with the product. If you have any further questions or need assistance, the experts at Sport-Thieme are available to help.