To install the EVBOX Elvi charging station, please follow these step-by-step instructions:
1. Before installing the wall dock, ensure that the power line you're using is switched off on your service panel.
2. Make sure that the power line to Elvi is installed on a dedicated circuit breaker (MCB) on your service panel. The installation must incorporate an adequate residual-current device (RCD). The MCB must be in line with the capacity of the charging cable (3.7, 7.4, 11, 22 kW). If the amperage rating of the charging cable is different than the amperage rating of the MCB, you must change the station settings in the mobile app for station management and/or backend portal account as provided by the operator or service provider for this product.
3. Select a solid and flat vertical surface for installing the wall dock. Ensure that the surface is even and solid enough to resist a pull force of at least 100 kg.
4. Cut the drilling template from the packaging and place it onto the wall. Use a level device to align the template. Mark the 4 mounting points on the wall and remove the template.
5. Drill holes with a drill round 8 mm. Use the provided 8x65 mm plugs.
6. xxxx in the provided 5x70 mm screws using the supplied torx T25 bit until the remaining distance from the wall is 10 mm. This is necessary to be able to hook on the wall dock.
7. Mount the wall dock onto the wall and fasten the 4 screws.
8. Remove the protective rubber cap from the wall dock.
9. Undo the 4 corner screws (3x Torx T20 using the supplied T20 bit and 1x slotted using a regular flat-head screwdriver). Remove the transparent cover from the wall dock.
10. Measure the power cable's diameter and cut out the correct diameter of the rubber seal to allow the power cable and optional data cables to pass through. The rubber seal and strain relief are supplied in a separate bag in the box.
11. Feed the power line and optional data wiring through the rubber seal. The total length of the power line fed through the rubber seal must be 180 mm. Strip the power line over a length of 130 mm. In case of stranded (flexible) wiring, use wire end sleeves with a ferrule length of 12-15 mm and apply a square crimp for optimal fit into the connection terminals.
12. Assemble the strain relief. Depending on the feed wire's thickness, use either the small or large diameter on the strain relief. Place one part of the strain relief in the bottom of the wall dock. Place the feed wire over the bottom part of the strain relief and mount the rubber seal in the outer edge of the wall dock. Place the top part of the strain relief over the feed wire and use the two 4x40 mm screws and the Torx T20 head to mount the strain relief on the feed wire. Do not overtighten.
13. Connect the wires in their designated terminals and mount the transparent cover. Make sure no wiring is protruding from under the transparent cover. Tighten the bolts with the T20 bit. Do not overtighten. Fasten the special bolt in the bottom right corner with a regular flat-head screwdriver. This special bolt can be used for sealing the installation with a tamper-evident seal.
14. The wall dock is now ready for Elvi installation. Align the charging station against the wall dock and press it in a straight line until you hear a clicking sound. Press firmly on all four corners to ensure a secure connection.
15. Switch on the power to the station on the service panel. Elvi will switch on automatically, indicated by a flashing red LED ring.
Please note that these instructions are a summary of the installation process. For more detailed information and safety precautions, please refer to the EVBOX Elvi V3 22 kW Socket Satellite, white Instruction Manual.