Answer
![manuals.plus](https://data3.answerbase.com/answerbase/15673/UserFiles/User3627018/profileImage3627018.jpg?638365818380000000)
Feb 01, 2025 - 12:06 AM
To properly install the ZT50M14 piezo actuator for cage structure, please follow these steps:
1. Ensure that the installation plane is flat.
2. Secure the piezo actuator with M6 screws and tighten them.
3. Install the load and tighten it properly to ensure positioning accuracy.
4. Connect the cable to the corresponding interface of the controller according to the connector.
It is important to use the recommended connection method and avoid using screws that are either too long or too short. Slowly tighten the load during installation to avoid damaging the mechanism. Additionally, be careful not to stretch or bend the cables and use the dedicated cable provided by CoreMorrow to connect the piezo actuator and the piezo controller.