To install the ventev 230106 Universal Stadium Handrail Enclosure, follow these steps:
1. Assembled Enclosure: The enclosure is shipped assembled. Remove the two screws with washers from each plastic shell to expose the metal mounting frame. Save the screws with washers for final assembly.
2. Cisco Access Point (AP) Installation: Remove the AP mounting bracket from the frame by disconnecting the four screws. Position the AP high enough for the AP feet to engage into the keyhole slots. Slide the AP downward into the slots.
3. Aruba AP Installation: For new Aruba APs, remove the two screws supplied with the AP and align the back of the AP with the horizontal slot in the AP mounting bracket. Install the two small screws that come with the AP. For older Aruba APs, place the round pegs into the clearance half holes and slide the AP downwards. Secure with a supplied #10-32 xxxx .
4. Antenna Installation: Install the antennas onto the top of the frame using the supplied screws and nuts. The antennas mount back-to-back, pointing 180 degrees from each other.
5. Remove Railing Brackets: Loosen the two screws that hold each of the three railing brackets to the metal frame and slide the brackets off.
6. Mount Metal Frame: Mount the metal mounting plate to the railing. Slide railing brackets into position and tighten screws. Bend the metal conduit (not supplied) entering the bottom of the enclosure to enter perpendicular to the handrail if the rails are not horizontal.
7. Seal Location: Mark the six positions where the seals will be installed between the outer lip of the enclosure shell and the metal frame, and under the rail clamp.
8. Seal Installation: Cut the flexible seals to the required length. Wrap the seal with the provided weatherproof fusion black tape to hold it in place and create a seal.
9. Clamp Frame: With the seals in place, clamp the frame to the handrail in three places.
10. Wire Routing: Route the RF cables inside the large aluminum standoffs to avoid interference with the weather seal.
11. Plastic Shell Installation: Fasten both enclosure shells to the metal frame with eight bolts per side. Tighten to 8 FT-LBS.
12. Caulk Area: Run a bead of caulk where the handrail enters the enclosure for better weather protection.
13. Service Label: Use the provided label to mark the equipment (AP) side shell for easier maintenance.