To install the Ventair SUNB1000BL Infrared Outdoor Heater, please follow these steps:
1. Before installation, ensure that the main electricity supply is turned off. Do not turn it back on until the heater is fully installed and ready to use.
2. It is recommended to have the heater installed by a qualified electrician.
3. For ceiling mounting, ensure that the lowest part of the heater is located at or above a minimum height of 1.8m from ground level, so that the heater cannot be touched when in operation.
4. Ensure there is a minimum distance of 0.5m between the corners and the appliance when installed to the ceiling.
5. The heater should always have a minimum clearance of 0.5m from a ceiling and adjacent wall.
6. Fasten the brackets securely to the mounting surface and the backside of the heater using the nuts and screws provided.
7. Adjust the direction of the heater by loosening the two bolts on the wall mounting bracket and tightening them again when the desired angle is reached.
8. For bathroom installations, ensure that switches and other controls cannot be touched by a person in the bath or shower.